from SAT 12:00 PM MST until SAT 10:00 PM MST, Western Pima County including Ajo/Organ Pipe Cactus National Monument, Tohono O'odham Nation including Sells, Upper Santa Cruz River and Altar Valleys including Nogales, Tucson Metro Area including Tucson/Green Valley/Marana/Vail, South Central Pinal County including Eloy/Picacho Peak State Park, Southeast Pinal County including Kearny/Mammoth/Oracle, Upper San Pedro River Valley including Sierra Vista/Benson, Eastern Cochise County below 5000 ft including Douglas/Wilcox, Upper Gila River and Aravaipa Valleys including Clifton/Safford, White Mountains of Graham and Greenlee Counties including Hannagan Meadow, Galiuro and Pinaleno Mountains including Mount Graham, Chiricahua Mountains including Chiricahua National Monument, Dragoon/Mule/Huachuca and Santa Rita Mountains including Bisbee/Canelo Hills/Madera Canyon, Santa Catalina and Rincon Mountains including Mount Lemmon/Summerhaven, Baboquivari Mountains including Kitt Peak, Kofa, Central La Paz, Aguila Valley, Southeast Yuma County, Gila River Valley, Northwest Valley, Tonopah Desert, Gila Bend, Buckeye/Avondale, Cave Creek/New River, Deer Valley, Central Phoenix, North Phoenix/Glendale, New River Mesa, Scottsdale/Paradise Valley, Rio Verde/Salt River, East Valley, Fountain Hills/East Mesa, South Mountain/Ahwatukee, Southeast Valley/Queen Creek, Superior, Northwest Pinal County, West Pinal County, Apache Junction/Gold Canyon, Tonto Basin, Mazatzal Mountains, Pinal/Superstition Mountains, Sonoran Desert Natl Monument, San Carlos, Dripping Springs, Globe/Miami, Southeast Gila County

Valley Metro tests light rail extension with water bottles

Water bottles came in handy Thursday morning as Valley Metro tested out some light rail cars for their planned expansion into Mesa.

Instead of passengers on board, tons of water bottles filled the rail cars.

Valley Metro hopes to open the Central Mesa light rail extension in August, but before that happens the new line needs to be tested, and that is where these 210,000 pounds of water bottles come in handy.

"We brainstormed some ideas on how to load the train, it is supposed to be loaded with 35,700 pounds per car, which is about 180 adults on the train at a time," said Chris Chaffe.

Valley Metro conductors are making sure the 3.1-mile extension is safe. So they loaded 105 tons of water onto the trains, that's 184,000 bottles. The bottles were loaded onto the cars at the Valley Metro Operations and Maintenance Center. The goal, to test the power on the new route.

"Our test is to load the train as if it were loaded with people, at the end of the day we get to donate the water, we're meeting 50% of their water needs for this summer," said Chafe.

When the testing wraps up, all of the bottled water will be donated to the United Food Bank.

"How exciting, I'm so glad we're gonna have water, and people are not gonna be dehydrated in our community... what a win-win situation for the entire community" said Melissa Forrester with the United Food Bank.

Testing runs through Monday. The project is months ahead of schedule, Valley Metro hopes to extend the light rail service on August 22nd.